What is established
Announced. 500 MW announced (basis not stated by the source); $1.2B announced investment; owned or developed by Nexus Core Systems.
What is not disclosed
Accelerator count, timeline, named tenant, power source, cooling technology — not disclosed by any source on this page. Recorded as unknown, never as zero.
Analyst note
Consortium with NAVER, NVIDIA and Lloyd Capital; first phase 40 MW with GB200s, staged toward a 500 MW target; renewable supply via TAQA. Construction start not independently confirmed, so ANNOUNCED. Would be among Africa's largest AI facilities.
Corroborated by more than one source, but not yet backed by physical evidence.
Power readiness
Capacity basis unclear
A megawatt figure exists but the source does not say whether it is IT load, site power or generation.
Derived from the evidence on this page by a published rule, not a model. How this is calculated.
NVIDIA GB200
33.3670, -7.5770
No companies linked to this project yet.
| Metric | Value | Confidence | As of | Basis / methodology | Source |
|---|---|---|---|---|---|
| Power | 500 MW | Medium | Not disclosed | Basis: unclear. Announced target, not energized capacity. Note: Consortium with NAVER, NVIDIA and Lloyd Capital; first phase 40 MW with GB200s, staged toward a 500 MW target; renewable supply via TAQA. Construction start not independently confirmed, so ANNOUNCED. Would be among Africa's largest AI facilities. | Middle East AI News |
| Capex | $1,200,000,000 | Medium | Not disclosed | Announced investment figure. | Middle East AI News |
DataCenterDynamics · Not disclosed · accessed Jul 28, 2026
Naver plans 500MW data center campus in Morocco
Reliability
78/100
Middle East AI News · Jun 13, 2025 · accessed Jul 28, 2026
Construction begins in Q4 2025 with a 40MW phase deploying NVIDIA's latest Blackwell GB200 GPUs
Reliability
65/100
Consortium with NAVER, NVIDIA and Lloyd Capital; first phase 40 MW with GB200s, staged toward a 500 MW target; renewable supply via TAQA. Construction start not independently confirmed, so ANNOUNCED. Would be among Africa's largest AI facilities.
No revisions recorded.