What is established
Under construction. expected Dec 2026; owned or developed by Microsoft.
What is not disclosed
Capacity, accelerator count, hardware platform, project capex, named tenant, power source, cooling technology — not disclosed by any source on this page. Recorded as unknown, never as zero.
Analyst note
Flagship of Microsoft's $17.5B 2026–2029 India commitment (country-wide figure, so no site capex recorded). Three availability zones; targeted live mid-2026. No site MW disclosed.
Physical work is under way and the evidence includes a primary source.
Power readiness
No capacity disclosed
No megawatt figure has been sourced for this project.
Derived from the evidence on this page by a published rule, not a model. How this is calculated.
17.3850, 78.4870
No companies linked to this project yet.
No metrics recorded
Add a claim from the source inbox to start the evidence trail for this project.
Microsoft · Dec 9, 2025 · accessed Jul 28, 2026
We will have the largest hyperscale presence in India with our new datacenter going live mid-2026
Reliability
95/100
Flagship of Microsoft's $17.5B 2026–2029 India commitment (country-wide figure, so no site capex recorded). Three availability zones; targeted live mid-2026. No site MW disclosed.
No revisions recorded.
Microsoft · Mount Pleasant, Wisconsin, United States
Tata Group · India
Reliance Industries · Jamnagar, Gujarat, India
Microsoft · Atlanta, Georgia, United States
Google · Visakhapatnam, Andhra Pradesh, India
Microsoft · Pecos, Texas, United States