What is established
Announced. 1.5 GW announced (basis not stated by the source); $5B announced investment; expected Dec 2028; owned or developed by DataVolt.
What is not disclosed
Accelerator count, hardware platform, named tenant, power source, cooling technology — not disclosed by any source on this page. Recorded as unknown, never as zero.
Analyst note
1.5 GW total campus target, basis unstated; capex of $5B covers phase one only, with the first ~300 MW targeted for 2028. NEOM megaprojects have a documented history of rescoping and no construction on this campus is documented as of mid-2026 — treat scale as aspirational.
Corroborated by more than one source, but not yet backed by physical evidence.
Power readiness
Capacity basis unclear
A megawatt figure exists but the source does not say whether it is IT load, site power or generation.
Derived from the evidence on this page by a published rule, not a model. How this is calculated.
27.9000, 35.3000
No companies linked to this project yet.
| Metric | Value | Confidence | As of | Basis / methodology | Source |
|---|---|---|---|---|---|
| Power | 1,500 MW | High | Not disclosed | Basis: unclear. Announced target, not energized capacity. Note: 1.5 GW total campus target, basis unstated; capex of $5B covers phase one only, with the first ~300 MW targeted for 2028. NEOM megaprojects have a documented history of rescoping and no construction on this campus is documented as of mid-2026 — treat scale as aspirational. | NEOM |
| Capex | $5,000,000,000 | High | Not disclosed | Announced investment figure. | NEOM |
NEOM · Feb 10, 2025 · accessed Jul 28, 2026
phase one – funded by an initial investment of USD 5 billion – expected to be operational by 2028
Reliability
95/100
DataCenterDynamics · Not disclosed · accessed Jul 28, 2026
The first 300MW phase of the site will reportedly go live in 2028
Reliability
78/100
1.5 GW total campus target, basis unstated; capex of $5B covers phase one only, with the first ~300 MW targeted for 2028. NEOM megaprojects have a documented history of rescoping and no construction on this campus is documented as of mid-2026 — treat scale as aspirational.
No revisions recorded.