New Albany, Ohio campus targeting 1 GW, with nuclear supply agreements signed in January 2026.
What is established
Partially operational. 1 GW announced (basis not stated by the source); expected Jun 2027; owned or developed by Meta; power source: Nuclear PPAs + grid.
What is not disclosed
Accelerator count, hardware platform, project capex, named tenant, cooling technology — not disclosed by any source on this page. Recorded as unknown, never as zero.
Analyst note
Nuclear agreements with TerraPower, Oklo and Vistra are power-purchase commitments, not on-site reactors delivering today. UPDATE 2026-08-01: Epoch lists Prometheus operational at an estimated 631 MW IT (854 MW projected by Q4 2026) against the ~1 GW announced cluster scale. Status moved to partially operational; the 1 GW figure remains the announced nameplate. Not operator-confirmed capacity, so nothing enters the confirmed column.
Corroborated by more than one source, but not yet backed by physical evidence.
Power readiness
Capacity basis unclear
A megawatt figure exists but the source does not say whether it is IT load, site power or generation.
Derived from the evidence on this page by a published rule, not a model. How this is calculated.
40.0810, -82.8088
| Company | Role | Ticker | Notes |
|---|---|---|---|
| TerraPower | Power equipment supplier | — | Nuclear PPA |
| Oklo | Power equipment supplier | OKLO | Nuclear PPA |
| Vistra | Utility | VST | Nuclear PPA |
| Metric | Value | Confidence | As of | Basis / methodology | Source |
|---|---|---|---|---|---|
| Power | 1,000 MW | Medium | Not disclosed | Reported operational capacity target. | NextBigFuture |
| Power | 631 MW | Estimated | Not disclosed | Basis: IT load. Epoch AI's satellite-derived directory estimate — an analyst figure, not an operator statement, recorded at ESTIMATED confidence. | Epoch AI |
NextBigFuture · Not disclosed · accessed Jul 26, 2026
Trade-press compilation of announced capacity. Figures require primary-source confirmation.
Reliability
55/100
Epoch AI · May 28, 2026 · accessed Aug 1, 2026
631 MW
Reliability
85/100
Nuclear agreements with TerraPower, Oklo and Vistra are power-purchase commitments, not on-site reactors delivering today. UPDATE 2026-08-01: Epoch lists Prometheus operational at an estimated 631 MW IT (854 MW projected by Q4 2026) against the ~1 GW announced cluster scale. Status moved to partially operational; the 1 GW figure remains the announced nameplate. Not operator-confirmed capacity, so nothing enters the confirmed column.
Update: Prometheus is running — status → PARTIALLY_OPERATIONAL, Epoch estimates 631 MW IT of the ~1 GW nameplate
Aug 1, 2026
System
Created from NextBigFuture reporting.
Jul 26, 2026
System
Oracle · Abilene, Texas, United States
Galaxy Digital · Dickens, Texas (Dickens County), United States
Nebius Group · Butler Township, Pennsylvania, United States
Applied Digital · Ellendale, North Dakota (Dickey County), United States
xAI · Memphis, Tennessee, United States
Related Digital · Saline Township, Michigan, United States