Anchor site of the Stargate programme in Abilene, Texas, operated by Oracle with OpenAI as tenant.
What is established
Partially operational. 200 MW confirmed energized (basis not stated by the source); expected Dec 2026; owned or developed by Oracle; tenant: OpenAI; power source: Grid + on-site gas turbines.
What is not disclosed
Accelerator count, project capex, cooling technology — not disclosed by any source on this page. Recorded as unknown, never as zero.
Analyst note
Gas turbines rated up to ~300 MW are reported on site, bridging the gap while grid capacity is built. CORRECTION 2026-08-01: the previous 300 MW confirmed figure was Epoch's April total-facility-power estimate, which Epoch itself revised. Oracle stated 'In Abilene, 200MW is already operational' (April 2026) — that operator statement is what the confirmed column now carries. Epoch's live directory estimates 421 MW IT across Buildings 1–4 (May 2026), projecting 843 MW / all eight buildings by ~November 2026; recorded as a separate estimate. OpenAI capped the site at 1.2 GW in March 2026.
Corroborated by more than one source, but not yet backed by physical evidence.
Power readiness
Operating capacity confirmed
A source states capacity that is energized and serving load.
Derived from the evidence on this page by a published rule, not a model. How this is calculated.
Estimate at full build: 1,200 MW
NVIDIA GB200 NVL72
32.4487, -99.7331
| Metric | Value | Confidence | As of | Basis / methodology | Source |
|---|---|---|---|---|---|
| Power | 1,200 MW | Medium | Not disclosed | Reported full-site target. | Data Center Knowledge |
| Power | 300 MW | Medium | Not disclosed | Reported on-site gas turbine capacity — generation, not IT load. Recorded separately to avoid conflating the two. | Data Center Knowledge |
| Power | 300 MW | Confirmed | Not disclosed | Basis: IT load. 200 MW operator-confirmed operating (Oracle, April 2026). Site target 1.2 GW. | Epoch AI |
| Power | 421 MW | Estimated | Not disclosed | Basis: IT load. Epoch AI's satellite-derived directory estimate — an analyst figure, not an operator statement, recorded at ESTIMATED confidence. Buildings 1–4 operational; 843 MW projected by Q4 2026. | Epoch AI |
Data Center Knowledge · Not disclosed · accessed Jul 26, 2026
Trade-press compilation of announced capacity. Figures require primary-source confirmation.
Reliability
75/100
Epoch AI · Not disclosed · accessed Jul 27, 2026
Reliability
80/100
Epoch AI · May 23, 2026 · accessed Aug 1, 2026
Buildings 3 and 4 are estimated to be operational... 'In Abilene, 200MW is already operational'
Reliability
85/100
Gas turbines rated up to ~300 MW are reported on site, bridging the gap while grid capacity is built. CORRECTION 2026-08-01: the previous 300 MW confirmed figure was Epoch's April total-facility-power estimate, which Epoch itself revised. Oracle stated 'In Abilene, 200MW is already operational' (April 2026) — that operator statement is what the confirmed column now carries. Epoch's live directory estimates 421 MW IT across Buildings 1–4 (May 2026), projecting 843 MW / all eight buildings by ~November 2026; recorded as a separate estimate. OpenAI capped the site at 1.2 GW in March 2026.
Correction: confirmed operating 300→200 MW (Oracle's own statement); Epoch's 421 MW IT added as a labelled estimate
Aug 1, 2026
System
Created from Data Center Knowledge reporting.
Jul 26, 2026
System
Galaxy Digital · Dickens, Texas (Dickens County), United States
Nebius Group · Butler Township, Pennsylvania, United States
Related Digital · Saline Township, Michigan, United States
Applied Digital · Ellendale, North Dakota (Dickey County), United States
Meta · New Albany, Ohio, United States
Crusoe Energy · Abilene, Texas, United States