What is established
Announced. 240 MW announced (basis not stated by the source); 104,000 accelerators (NVIDIA GB300 NVL72); owned or developed by Nscale.
What is not disclosed
Project capex, timeline, named tenant, power source, cooling technology — not disclosed by any source on this page. Recorded as unknown, never as zero.
Analyst note
Site leased from Ionic Digital; fourth Nscale–Microsoft deal, reported at up to $24B (contract value, not capex). Construction from Q3 2026; Microsoft holds an option for a further 700 MW from Q1 2027. 240 MW initial, expandable to 1.2 GW; basis unstated. GPU count is the announced deployment plan.
Corroborated by more than one source, but not yet backed by physical evidence.
Power readiness
Capacity basis unclear
A megawatt figure exists but the source does not say whether it is IT load, site power or generation.
Derived from the evidence on this page by a published rule, not a model. How this is calculated.
NVIDIA GB300 NVL72
31.4630, -103.3980
No companies linked to this project yet.
| Metric | Value | Confidence | As of | Basis / methodology | Source |
|---|---|---|---|---|---|
| Power | 240 MW | Medium | Not disclosed | Basis: unclear. Announced target, not energized capacity. Note: Site leased from Ionic Digital; fourth Nscale–Microsoft deal, reported at up to $24B (contract value, not capex). Construction from Q3 2026; Microsoft holds an option for a further 700 MW from Q1 2027. 240 MW initial, expandable to 1.2 GW; basis unstated. GPU count is the announced deployment plan. | Bloomberg |
| GPU count | 104,000 GPUs | Medium | Not disclosed | Model: NVIDIA GB300 NVL72. | Bloomberg |
Bloomberg · Oct 15, 2025 · accessed Jul 28, 2026
capacity of as much as 240 megawatts of power, with the company planning to increase that number to 1.2 gigawatts over time
Reliability
85/100
SiliconANGLE · Oct 15, 2025 · accessed Jul 28, 2026
Nscale will start building a second, significantly larger facility in Texas during the third quarter of 2026 ... about 104,000 GPUs
Reliability
65/100
Site leased from Ionic Digital; fourth Nscale–Microsoft deal, reported at up to $24B (contract value, not capex). Construction from Q3 2026; Microsoft holds an option for a further 700 MW from Q1 2027. 240 MW initial, expandable to 1.2 GW; basis unstated. GPU count is the announced deployment plan.
No revisions recorded.
Oracle · Abilene, Texas, United States
Galaxy Digital · Dickens, Texas (Dickens County), United States
Nscale · North Tyneside, North East England, United Kingdom
Nebius Group · Butler Township, Pennsylvania, United States
Nscale · Loughton, Essex, United Kingdom
Nscale · Narvik, Nordland, Norway