What is established
Under construction. 500 MW announced (gross site power); $10B announced investment; owned or developed by Compass Datacenters.
What is not disclosed
Accelerator count, hardware platform, timeline, named tenant, power source, cooling technology — not disclosed by any source on this page. Recorded as unknown, never as zero.
Analyst note
'The campus will consist of eight data centers that will be constructed over an eight-year period.' Compass leases build-to-suit to investment-grade hyperscalers; end tenant not officially disclosed (Meta widely speculated in trade press, unconfirmed). 500MW figure is utility supply (site power), not critical IT load. 10-year state tax exemptions granted.
Physical work is under way and the evidence includes a primary source.
Power readiness
Capacity basis stated
The source distinguishes IT load from total site power or on-site generation.
Derived from the evidence on this page by a published rule, not a model. How this is calculated.
32.3640, -88.7040
No companies linked to this project yet.
| Metric | Value | Confidence | As of | Basis / methodology | Source |
|---|---|---|---|---|---|
| Power | 500 MW | High | Not disclosed | Basis: site power. Announced target, not energized capacity. Note: 'The campus will consist of eight data centers that will be constructed over an eight-year period.' Compass leases build-to-suit to investment-grade hyperscalers; end tenant not officially disclosed (Meta widely speculated in trade press, unconfirmed). 500MW figure is utility supply (site power), not critical IT load. 10-year state tax exemptions granted. | Office of Governor Tate Reeves |
| Capex | $10,000,000,000 | High | Not disclosed | Announced investment figure. | Office of Governor Tate Reeves |
Office of Governor Tate Reeves · Jan 9, 2025 · accessed Jul 29, 2026
Upon occupancy, Compass Datacenters' campus will represent an investment of $10 billion. Mississippi Power will supply approximately 500 megawatts of power to the facility.
Reliability
95/100
'The campus will consist of eight data centers that will be constructed over an eight-year period.' Compass leases build-to-suit to investment-grade hyperscalers; end tenant not officially disclosed (Meta widely speculated in trade press, unconfirmed). 500MW figure is utility supply (site power), not critical IT load. 10-year state tax exemptions granted.
No revisions recorded.
Oracle · Abilene, Texas, United States
Galaxy Digital · Dickens, Texas (Dickens County), United States
Related Digital · Saline Township, Michigan, United States
Meta · New Albany, Ohio, United States
xAI · Memphis, Tennessee, United States
Applied Digital · Ellendale, North Dakota (Dickey County), United States