What is established
Under construction. 1 GW announced (basis not stated by the source); $10B announced investment; owned or developed by Meta.
What is not disclosed
Accelerator count, hardware platform, timeline, named tenant, power source, cooling technology — not disclosed by any source on this page. Recorded as unknown, never as zero.
Analyst note
Groundbreaking 2026-02-11; Meta's 27th US data center. Reported full operation late 2027/early 2028, recorded as no date since sources give a range. 1 GW basis (IT vs site) not specified.
Corroborated by more than one source, but not yet backed by physical evidence.
Power readiness
Capacity basis unclear
A megawatt figure exists but the source does not say whether it is IT load, site power or generation.
Derived from the evidence on this page by a published rule, not a model. How this is calculated.
40.0500, -86.4700
No companies linked to this project yet.
| Metric | Value | Confidence | As of | Basis / methodology | Source |
|---|---|---|---|---|---|
| Power | 1,000 MW | Medium | Not disclosed | Basis: unclear. Announced target, not energized capacity. Note: Groundbreaking 2026-02-11; Meta's 27th US data center. Reported full operation late 2027/early 2028, recorded as no date since sources give a range. 1 GW basis (IT vs site) not specified. | Data Center Knowledge |
| Capex | $10,000,000,000 | Medium | Not disclosed | Announced investment figure. | Data Center Knowledge |
DataCenterDynamics · Not disclosed · accessed Jul 28, 2026
approximately $10 billion invested in data center infrastructure and the surrounding community
Reliability
78/100
Data Center Knowledge · Feb 12, 2026 · accessed Jul 28, 2026
1 GW campus in Lebanon, Ind., designed to handle AI workloads
Reliability
65/100
Groundbreaking 2026-02-11; Meta's 27th US data center. Reported full operation late 2027/early 2028, recorded as no date since sources give a range. 1 GW basis (IT vs site) not specified.
No revisions recorded.
Oracle · Abilene, Texas, United States
Galaxy Digital · Dickens, Texas (Dickens County), United States
Nebius Group · Butler Township, Pennsylvania, United States
Applied Digital · Ellendale, North Dakota (Dickey County), United States
Meta · New Albany, Ohio, United States
Related Digital · Saline Township, Michigan, United States