What is established
Paused. 2 GW announced (gross site power); owned or developed by Poolside.
What is not disclosed
Accelerator count, hardware platform, project capex, timeline, named tenant, power source, cooling technology — not disclosed by any source on this page. Recorded as unknown, never as zero.
Analyst note
2GW campus on 568 acres of the Mitchell family's Longfellow Ranch, gas-rich Permian Basin site. CoreWeave was anchor tenant (15-yr lease, 250MW first phase expandable to 500MW, planned 40,000+ GB300 NVL72 GPUs) but the deal was mutually terminated in early 2026; Poolside approached other clouds incl. Google ('Google is no longer in talks with Poolside'). Power figure is planned gross site power, none operating. CORRECTION 2026-08-01: the CoreWeave anchor lease was terminated in late March 2026 after Poolside's ~$2B raise failed to close; the site sits idle. A scaled-down ~400 MW revival with Google was mooted and those talks have gone quiet. The 2 GW figure remains the announced campus plan only; PAUSED removes it from the credible pipeline.
Corroborated by more than one source, but not yet backed by physical evidence.
Power readiness
Capacity basis stated
The source distinguishes IT load from total site power or on-site generation.
Derived from the evidence on this page by a published rule, not a model. How this is calculated.
30.8940, -102.8790
No companies linked to this project yet.
| Metric | Value | Confidence | As of | Basis / methodology | Source |
|---|---|---|---|---|---|
| Power | 2,000 MW | Medium | Not disclosed | Basis: site power. Announced target, not energized capacity. Note: 2GW campus on 568 acres of the Mitchell family's Longfellow Ranch, gas-rich Permian Basin site. CoreWeave was anchor tenant (15-yr lease, 250MW first phase expandable to 500MW, planned 40,000+ GB300 NVL72 GPUs) but the deal was mutually terminated in early 2026; Poolside approached other clouds incl. Google ('Google is no longer in talks with Poolside'). Power figure is planned gross site power, none operating. | Data Center Frontier |
Baxtel · Apr 4, 2026 · accessed Jul 29, 2026
The partnership with CoreWeave began to unravel late last year after Poolside failed to deploy its first chip cluster.
Reliability
65/100
Data Center Frontier · Oct 1, 2025 · accessed Jul 29, 2026
2 gigawatt (GW) AI campus on 568 acres of development-ready land in West Texas
Reliability
78/100
2GW campus on 568 acres of the Mitchell family's Longfellow Ranch, gas-rich Permian Basin site. CoreWeave was anchor tenant (15-yr lease, 250MW first phase expandable to 500MW, planned 40,000+ GB300 NVL72 GPUs) but the deal was mutually terminated in early 2026; Poolside approached other clouds incl. Google ('Google is no longer in talks with Poolside'). Power figure is planned gross site power, none operating. CORRECTION 2026-08-01: the CoreWeave anchor lease was terminated in late March 2026 after Poolside's ~$2B raise failed to close; the site sits idle. A scaled-down ~400 MW revival with Google was mooted and those talks have gone quiet. The 2 GW figure remains the announced campus plan only; PAUSED removes it from the credible pipeline.
Status correction: ANNOUNCED → PAUSED — CoreWeave lease terminated March 2026, site idle, revival talks quiet
Aug 1, 2026
System
Oracle · Abilene, Texas, United States
Galaxy Digital · Dickens, Texas (Dickens County), United States
Nebius Group · Butler Township, Pennsylvania, United States
Applied Digital · Ellendale, North Dakota (Dickey County), United States
Meta · New Albany, Ohio, United States
Related Digital · Saline Township, Michigan, United States