What is established
Planning. 1.3 GW announced (gross site power); owned or developed by Prometheus Hyperscale.
What is not disclosed
Accelerator count, hardware platform, project capex, timeline, named tenant, power source, cooling technology — not disclosed by any source on this page. Recorded as unknown, never as zero.
Analyst note
506-acre site on founder Trenton Thornock's family ranch; unanimous Uinta County conditional-use approval June 2026. 'Prometheus says construction will begin within six months of final permitting and take four to five years.' Mostly natural-gas powered, closed-loop water-glycol cooling. Capex null: reported $30B covers two Wyoming projects (Evanston plus a proposed Casper-area site), not this campus alone. Former BP CEO Bernard Looney leads the buildout. Some reports cite expansion potential to 5GW.
Corroborated by more than one source, but not yet backed by physical evidence.
Power readiness
Capacity basis stated
The source distinguishes IT load from total site power or on-site generation.
Derived from the evidence on this page by a published rule, not a model. How this is calculated.
41.2600, -110.7100
No companies linked to this project yet.
| Metric | Value | Confidence | As of | Basis / methodology | Source |
|---|---|---|---|---|---|
| Power | 1,250 MW | Medium | Not disclosed | Basis: site power. Announced target, not energized capacity. Note: 506-acre site on founder Trenton Thornock's family ranch; unanimous Uinta County conditional-use approval June 2026. 'Prometheus says construction will begin within six months of final permitting and take four to five years.' Mostly natural-gas powered, closed-loop water-glycol cooling. Capex null: reported $30B covers two Wyoming projects (Evanston plus a proposed Casper-area site), not this campus alone. Former BP CEO Bernard Looney leads the buildout. Some reports cite expansion potential to 5GW. | KPCW |
KPCW · Jun 19, 2026 · accessed Jul 29, 2026
The data center will run on 1.25 gigawatts, more electricity than all the homes in Wyoming use.
Reliability
65/100
Cowboy State Daily · Apr 1, 2026 · accessed Jul 29, 2026
Former BP CEO To Lead Prometheus Hyperscale's $30B Wyoming Data Center Buildout
Reliability
65/100
506-acre site on founder Trenton Thornock's family ranch; unanimous Uinta County conditional-use approval June 2026. 'Prometheus says construction will begin within six months of final permitting and take four to five years.' Mostly natural-gas powered, closed-loop water-glycol cooling. Capex null: reported $30B covers two Wyoming projects (Evanston plus a proposed Casper-area site), not this campus alone. Former BP CEO Bernard Looney leads the buildout. Some reports cite expansion potential to 5GW.
No revisions recorded.
Oracle · Abilene, Texas, United States
Galaxy Digital · Dickens, Texas (Dickens County), United States
Nebius Group · Butler Township, Pennsylvania, United States
Applied Digital · Ellendale, North Dakota (Dickey County), United States
Meta · New Albany, Ohio, United States
Related Digital · Saline Township, Michigan, United States