What is established
Announced. 1 GW announced (gross site power); $10B announced investment; owned or developed by QTS Data Centers.
What is not disclosed
Accelerator count, hardware platform, timeline, named tenant, power source, cooling technology — not disclosed by any source on this page. Recorded as unknown, never as zero.
Analyst note
Up to 11 QTS-built buildings on 465 acres at Lancium's Clean Campus; 'The site is supported by a 1GW grid connection.' On-site solar plus battery storage, closed-loop cooling; up to 7,000 peak construction jobs, ~350 permanent. No construction start or opening dates announced. Separate from Blackstone/QTS's $25B Pennsylvania commitment and the abandoned 2,100-acre Virginia Digital Gateway.
Corroborated by more than one source, but not yet backed by physical evidence.
Power readiness
Capacity basis stated
The source distinguishes IT load from total site power or on-site generation.
Derived from the evidence on this page by a published rule, not a model. How this is calculated.
34.3930, -100.8960
No companies linked to this project yet.
| Metric | Value | Confidence | As of | Basis / methodology | Source |
|---|---|---|---|---|---|
| Power | 1,000 MW | High | Not disclosed | Basis: site power. Announced target, not energized capacity. Note: Up to 11 QTS-built buildings on 465 acres at Lancium's Clean Campus; 'The site is supported by a 1GW grid connection.' On-site solar plus battery storage, closed-loop cooling; up to 7,000 peak construction jobs, ~350 permanent. No construction start or opening dates announced. Separate from Blackstone/QTS's $25B Pennsylvania commitment and the abandoned 2,100-acre Virginia Digital Gateway. | QTS (press release) |
| Capex | $10,000,000,000 | High | Not disclosed | Announced investment figure. | QTS (press release) |
QTS (press release) · Jul 13, 2026 · accessed Jul 29, 2026
a data center campus expected to bring more than $10 billion in capital investment to the region
Reliability
95/100
Baxtel · Jul 1, 2026 · accessed Jul 29, 2026
The companies plan to invest $10 billion to build up to 11 data center buildings across 465 acres near Turkey, Texas.
Reliability
65/100
Up to 11 QTS-built buildings on 465 acres at Lancium's Clean Campus; 'The site is supported by a 1GW grid connection.' On-site solar plus battery storage, closed-loop cooling; up to 7,000 peak construction jobs, ~350 permanent. No construction start or opening dates announced. Separate from Blackstone/QTS's $25B Pennsylvania commitment and the abandoned 2,100-acre Virginia Digital Gateway.
No revisions recorded.
Oracle · Abilene, Texas, United States
Galaxy Digital · Dickens, Texas (Dickens County), United States
Nebius Group · Butler Township, Pennsylvania, United States
Applied Digital · Ellendale, North Dakota (Dickey County), United States
Meta · New Albany, Ohio, United States
Related Digital · Saline Township, Michigan, United States