What is established
Under construction. 902 MW announced (critical it load); $15B announced investment; expected Dec 2028; owned or developed by Vantage Data Centers.
What is not disclosed
Accelerator count, hardware platform, named tenant, power source, cooling technology — not disclosed by any source on this page. Recorded as unknown, never as zero.
Analyst note
One of the five Stargate sites announced 2025-09-23. 902 MW across four buildings per local reporting of the approved plan; Vantage's own words are 'close to a gigawatt of AI capacity' (IT). Site draw reported at 1.3 GW with later phases potentially to 3.5 GW. Groundbreaking Dec 2025, completion scheduled 2028.
Physical work is under way and the evidence includes a primary source.
Power readiness
Capacity basis stated
The source distinguishes IT load from total site power or on-site generation.
Derived from the evidence on this page by a published rule, not a model. How this is calculated.
43.3872, -87.8756
No companies linked to this project yet.
| Metric | Value | Confidence | As of | Basis / methodology | Source |
|---|---|---|---|---|---|
| Power | 902 MW | High | Not disclosed | Basis: IT load. Announced target, not energized capacity. Note: One of the five Stargate sites announced 2025-09-23. 902 MW across four buildings per local reporting of the approved plan; Vantage's own words are 'close to a gigawatt of AI capacity' (IT). Site draw reported at 1.3 GW with later phases potentially to 3.5 GW. Groundbreaking Dec 2025, completion scheduled 2028. | Vantage Data Centers |
| Capex | $15,000,000,000 | High | Not disclosed | Announced investment figure. | Vantage Data Centers |
Vantage Data Centers · Oct 22, 2025 · accessed Jul 28, 2026
The campus will feature four cutting-edge data centers providing close to a gigawatt of AI capacity.
Reliability
95/100
BizTimes Milwaukee · Dec 17, 2025 · accessed Jul 28, 2026
The data center is expected to use 1.3 gigawatts of power, with later phases potentially requiring up to 3.5 gigawatts.
Reliability
65/100
One of the five Stargate sites announced 2025-09-23. 902 MW across four buildings per local reporting of the approved plan; Vantage's own words are 'close to a gigawatt of AI capacity' (IT). Site draw reported at 1.3 GW with later phases potentially to 3.5 GW. Groundbreaking Dec 2025, completion scheduled 2028.
No revisions recorded.
Oracle · Abilene, Texas, United States
Galaxy Digital · Dickens, Texas (Dickens County), United States
Nebius Group · Butler Township, Pennsylvania, United States
Applied Digital · Ellendale, North Dakota (Dickey County), United States
Meta · New Albany, Ohio, United States
Related Digital · Saline Township, Michigan, United States